There are a number of major construction projects currently occurring in White Rock's Town Centre Area. You can learn more about the construction management plans for these projects below:

CDCL

A Construction Management Plan was presented at a Committee of the Whole meeting on October 15, 2007 that outlines both the proposed truck routes and the construction staging. A copy of the presentation can be viewed below.
Click here to see CDCL Construction Management Plan (PDF)
BOSA PROPERTIES
MIRAMAR VILLAGE

CONSTRUCTION MANAGEMENT INFORMATION

The construction of Phase I of Miramar Village consisting of the first two northerly towers has been commenced by Bosa Properties. City staff are working with Bosa to ensure that there is adequate information available to residents to ensure that they are aware of current and upcoming construction operations.

The intent is to have Bosa maintain a website that will provide information on their construction operations and any associated impacts on City streets. The City will provide a link to the Bosa property when available. In the short term the City will provide information and documents on the City's website for residents information.

Construction Management Plan

Bosa presented a Construction Management Plan at a Committee of the Whole on September 18, 2006 that outlined both the proposed truck routes and the construction staging. A copy of Bosa's presentation is attached that includes the Truck Route Map and the construction staging for Tower I & II.
Click here to see Construction Management Plan (PDF)

The construction timing may be briefly summarized as follows:
Action Start Date Estimated Duration
Demolition October 2006 One month
Excavation - Tower 1 November 2006 One month
Forming Tower 1 & Excavation Tower 2
(pumping concrete from Russell)
January 2007 Three months
Forming Towers 1 & 2
(pumping concrete from Russell & Johnston)
March 2007 Six months
Forming Typical Floor levels and Hoisting
Tower 1 (concrete hoisted by crane).
Tower 2 continuing to pump concrete.
September 2007 Two months
Hoisting Towers 1 & 2 (Concrete and supplies being delivered by crane) November 2007 Six months
Concrete Pours complete. Completing building finishes. May 2008 Six – seven months